Rental Tips
Data Centre Construction in Johor Bahru: A Sample Equipment Plan, Phase by Phase
By Jonah Tan, Equipment Specialist · · 5 min read

Note: this is an illustrative example, not a record of a past A&G Equipment project. The building, phases and quantities are a typical scenario, put together to show how contractors plan equipment for data centre construction in Johor Bahru. Machine figures come from our product pages.
Johor Bahru and the Kulai, Sedenak and Senai corridor have become one of the busiest data centre construction areas in the region. These projects run on tight, fixed handover dates, and aerial access and material handling are easy to underestimate until a crew is standing around waiting for a lift.
Here is how a mixed equipment fleet would typically be planned for a data centre build, phase by phase.
The example project
- Building: a two-storey data centre building with data halls, an electrical and mechanical plant area, and a rooftop with cooling equipment.
- Location: an industrial site in the Johor Bahru area (for example, Kulai or Sedenak).
- Contractors on site: the main contractor, plus M&E, cable tray, fire protection and cladding subcontractors working at the same time.
- The challenge: several trades need access at height at once, indoors and outdoors, while equipment deliveries arrive every day.
Phase 1: Structure, envelope and roof
The building is still open, and the ground outside is rough and changing every day.
| Task | Machine | Why |
|---|---|---|
| Cladding and façade panels | Dingli 44m telescopic boom lift or Dingli JCPT1823DCL rough-terrain scissor lift | Long reach from outside the building line, or a large deck for crews working along a wall |
| Lifting materials onto the roof and upper floors | Merlo telehandler | Lifts pallets and materials high and forward from rough ground |
| Unloading steel, panels and pallets | EP 7 ton diesel forklift | Heavy outdoor loads in the laydown yard |
Planning tip: agree the laydown area and the machine routes on day one. Telehandlers and boom lifts need firm, level ground to set up on, and trenches and backfill move around a lot during this phase.
Phase 2: M&E inside the data halls
The building is closed in, floors are finished, and cable trays, containment, fire protection and lighting go in overhead. This is where most of the aerial access hours are.
| Task | Machine | Why |
|---|---|---|
| Cable trays, containment, sprinklers | Dingli JCPT1412HD scissor lift (about 13.8 m working height, 320 kg) | Wide deck for two workers plus trays and tools |
| Lower ceilings, corridors, plant rooms | Dingli 12m electric scissor lift | Battery powered, non-marking tyres |
| Reaching over plant, pipework and racks | Dingli 16m or 18m electric articulating boom | The boom bends up and over obstructions; the 16m BA16NE is 1.73 m wide for tight routes |
Planning tips:
- Electric only indoors. No diesel fumes in data halls, where dust and exhaust are not acceptable.
- Check floor loading before machines go onto raised floors or upper slabs. Ask us for machine weights early.
- Protect finished floors along the routes the machines travel. Our floor protection guide covers how.
- Plan charging points so batteries are charged overnight, not during the shift.
Phase 3: Equipment install and commissioning
Generators, switchgear, UPS units, cooling units and server racks arrive in large numbers.
| Task | Machine | Why |
|---|---|---|
| Unloading and moving equipment indoors | EP 3–3.5 ton Li-ion forklift | No fumes, quiet, suits enclosed loading bays |
| Heavy outdoor items | EP 7 ton diesel forklift | Extra capacity in the yard |
| Final M&E, lighting and snagging at height | Scissor lifts kept on site from Phase 2 | Short jobs all over the building |
Never lift people on forklift forks during commissioning. For any work at height, keep a scissor lift or boom lift on site.
Phase 4: Handover
As trades finish, machines go off-hire in stages rather than all at once. Weekly or monthly rental terms make it easy to keep one or two scissor lifts for snagging and release the rest.
What makes a data centre equipment plan work
- Map heights early. List every height you need to reach, phase by phase, and match a working height to each. Working height is platform height plus about 2 m. See our scissor lift height guide.
- One supplier for the mixed fleet. Scissor lifts, boom lifts, forklifts and telehandlers from one company means one contact, one set of documents and one delivery plan.
- Documents approved before mobilisation. Data centre sites usually need PMA copies, servicing records and operator training records before a machine is allowed on site. Our PMA checklist lists what to prepare.
- Agreed breakdown response. On a fixed handover date, a machine that is down for two days costs more than its rental. Our rental customers get 24/7 breakdown support.
- Plan delivery windows. Large sites control gate times and laydown space. Book deliveries around them.
For a detailed checklist on booms, read boom lift rental for data centre projects in Johor.
Planning a data centre project in Johor Bahru?
A&G Equipment supplies scissor lifts, boom lifts, forklifts and telehandlers from our yard in Iskandar Puteri, with delivery across Johor Bahru, Kulai, Sedenak and Senai, and to KL & Selangor. Scissor lifts and boom lifts come with a valid PMA, every machine is serviced before delivery, and operator training is included. Rates are on enquiry.
See our data centre lift rental in Johor page, or WhatsApp us with your site location, phases and dates, and we will put together an equipment plan for your project.






